5th - 25th August 2002

The house is almost completely lined now and gib-stopping has started.  The external doors have also been delivered and stained and we're very pleased with them - worth the long wait.  Nathan has almost completed the plumbing and the electric Velux window has been installed in the upstairs toilet. 

Totally Plastered!

Glenn, Jason, & Steve putting the final coat on the back of the house

 

Alan's gib-lifter in action on the ceilings

 

Some of the difficult lining detail.  To make it worse the apex is 7 metres above the gallery floor.
Rodney, the gib-stopper hard at it.

 

View from the lounge through to the dining room.  The inside of the house is much lighter now that all of the doors are in and the ceilings have been lined.

 

Neville contemplating how the crows nest roof will look.
We have now set a tentative moving-in date of September 21st (6 months exactly from when the project started.